Methodology - How to rectify after rain cutting of side slope of formation bed of Railway Project.

Micro Step of information about Construction of Indian Railway Projects 

DFCCIL 

Methodology for Rain Cutting of Side Slope (1:2) of Formation Bed of Railway Track

      Contents:  

1. Purpose .................................................Page 2

   2. Scope .....................................................Page 2 

 3. Cross References ..................................Page 2  

4.   Construction Methodology .................Page 2    

          (I) Setting out and Marking ...............................................................Page 2   
         (II) Rectification of Rain cut on Slope ........................................... ....Page 3
        (III) Construction ..................................................................................Page 4
         (IV) Machinery Deployment ................................................................Page 5

                 Annextures

                          Check list for Slope Cutting
                          Operational Control Procedures for Excavation
                                                                                              
                                                                                                                         


  1. Purpose:
   
                        This submittal pertain to our proposed Methodology for the 
                         preparation of side slope 1:2 ratio as per approved cross section of
                         plan and profile.

    2.  Scope:

                   The Scope of this methodology cover following activities:
                    (I) Setting out and marking.
                   (II) Repair and compaction procedure foe existing rain cuts on slope.        
                  (III) Cutting of 500 mm extra width of formation to achieve side slope in 1:2 ratio.

     3.  Cross Reference:
                            
                    (I) Contract agreement documents/Technical Specification
                   (II)  RDSO/2007/GE-0014
                  (III)  All other applicable Indian Standard/Specification as mentioned
                            in contract agreement
                   (IV)  Morth

     4.  Construction Methodology:
          
                (I) Setting out and marking:                 
                                
                        (a) Center line of the formation      
                        (b) Toe line of the formation top
                        (c)  OGL toe of the formation
                        (b)  Fixing of pegs at every 10 m of formation top and toe of the OGL at either
                               side.
                         (e)  Marking will be done with the help of rope and measuring tape.

                (II) Rectification of Rain cuts on slope:   

                               Reference - Morth section 300
                               Affected portion will be surveyed jointly with client representatives for
                               classification of the rain cuts as follow.
                                   * Presence of rain cuts in the portion of slope cutting 0.5m.
                                   * Presence of rain cuts in the portion of final formation.
                               a)  Rectification procedure for presence of rain cuts in the 
                                    portion of slope cutting 0.50m.
                                    There is no separate rectification required for particular rain cuts. This 
                                     will be removed during final slope cutting prior to turfing activity.
                               b)  Rectification procedure for presence of rain cuts                                    in the portion of final formation.
                                     The areas affected by rain cuts shall be cleared of all loose soil and benched
                                     for the area of accessing the graders and rollers. Approved suitable fresh                                           material (SQ-2) shall be deposited in layers not exceeding 200mm thickness 
                                     and compacted so as to match with the benching at moisture content close                                         to the optimum. Compaction shall be carried out using suitable equipment
                                     such as vibratory rollers.Compaction test shall be made as per approved                                             FQP/ Specification. The finished work shall conform to the alignment, level
                                     and slopes as indicated in the drawing or as directed by the Engineer.

                   (III)  Construction:
                               a)  Cutting of 500mm extra width of formation on either sides to achieve 
                                      compacted side slope in the ratio 1:2 as per approved  plan and design.Cut
                                      soil will be removed from the site and that will be used further as suitable 
                                      location as embankment material as (SQ-1).
                                 b) The sequence of cutting will be starting from blanket layer to embankment 
                                      layer.
                                 c) This activity will be done with machinery- Excavator with mounted 
                                     blade/JCB/ Grader.
                                 d) To get proper and uniform surface of the slope dressing will be done by 
                                      spade/shovel by skilled labour.
                                 e) Whenever extra soil cutting more than 1:2 slope, soil will be placed on the 
                                      portion of pockets and compacted with suitable vibratory attachment of 
                                      excavator. 
                                  f) The cut slope shall be ensured with free from debris and undesirables 
                                      materials.
                                 g) To avoid any damage to the toe of the formation, slope arrangements                                                  /profiling shall be done in the toe of the formation for drain away the 
                                      surface run off from the toe.
                                 h) Existing additional slope shall be remain to strengthen and profiling to 
                                      drain away the surface run off  and avoid damage to the toe.
                                  j) Checking 1.5 m slant length template in 1:2 slope will be arrange at site for
                                      the checking of the desired slope.     


                      (IV) Machinery Deployment
                                  a) Excavator with mounted blade/Vibratory arrangements
                                  b) JCB
                                  c) Grader 
                                  d) Water Tanker   
                                  e) 3M Straight Edge                    